BKPM DO "DEBOTTLENECKING" SIX ELECTRICITY PROJECTS
Investment Coordinating Board (BKPM) in an
attempt to "de-bottlenecking" or facilitation of the six electricity
projects that are currently hampered the realization of investments.
"There are some constraints faced by
the six electricity project is being facilitated by BKPM, among others, the
issue of land acquisition, suitability RUPTL, public protests and guarantee the
supply of gas," said Deputy BKPM Investment Planning Tamba Hutapea in a
press release received by Antara in Jakarta on Wednesday .
Sixth total capacity of 8.136 MW project
consists of four coal-fired power plant project (PLTU) as well as the project
of geothermal power plants (PLTP) and a gas power plant project (PLTG).
The projects are located in Jambi, North
Sumatra, Central Java, Bali and Batam (Riau Islands).
"In addition to the six projects, it
is also possible facilitation of the other power projects that require the
attendance of the government to help find solutions to the problems faced
investment," said Tamba.
Based on data from BKPM, since trials One
Stop Services (OSS) Center on January 15 to 3 February, there are 12 licensing
projects proposed electricity through Central PTSP.
Three projects are foreign direct
investment (PMA) and nine domestic investment projects (PMDN) with a total
capacity of 257.8 MW.
The electrification project consists of six
hydropower projects / micro power plants, three solar projects and three power
plant projects spread across 11 provinces in North Sumatra, West Sulawesi,
Gorontalo, West Nusa Tenggara, West Java, Banten, South Kalimantan, East Nusa
Tenggara, Southeast Sulawesi, South Sulawesi and West Sumatra.
Head of BKPM Franky Sibarani said it uses
three strategies to accelerate electricity investment to support government
programs to build 35,000 MW power plant in five years.
The third strategy of
"de-bottlenecking" or facilitate the realization of projects delayed,
accelerate electricity through OSS licensing service centers and encourage
existing private power company to expand or expansion investment.
"BKPM will continue to oversee the
licensing process electrification project in order to fit the processing time
or even faster than the current standard operating procedures that apply,"
he said.
Franky said it continues to coordinate with
relevant ministries / agencies to determine the acceleration time from any
licensing process in the electricity sector.
"We expect the next three months can
already decided acceleration licensing electricity sector," he said.
According to Franky, the agency has
received more investment than 10 existing electricity companies to expand
investment.
The ten companies that are plan
electrification projects with total capacity of 11.369 MW.
Source form Indonesia Media :
http://www.antaranews.com/berita/478201/bkpm-lakukan-debottlenecking-enam-proyek-listrik